Relevant
Treasurer's Instruction(s)
Introduction
Contract
Documentation
Contract
Administration
Managing
Contractual Risk
Delegations
Resolution of
Contractual Disputes
Crown Contracts
Confidentiality Policy
Relevant
Treasurer's Instruction(s)
The
Treasurer's Instructions 1206, 1207, 1215, 1216, 1229 and
1401.
Introduction
Following is a brief summary of important
information in relation to contract documentation, delegation and
risk for building and construction procurement.
The Procurement Practices Manual - Contract Documentation, Delegation
and Risk sets out further guidance information in relation
to these matters for agencies primarily using the Crown
Solicitor's Building Construction Request for Tender
documentation and AS 2124-1992 (as amended by the Guides to
the Completion of Annexures to AS 2124-1992). However, it
also provides general guidance information for agencies in
preparation of other contract documentation as provided for under
the Treasurer's Instructions 1206 and 1207.
Contract
Documentation
A completed set of contractual documents
should consist of four distinct and separate parts to satisfy the
requirements of the tender process and adequately serve the
administration of the contract.
These parts are:
-
the Conditions of Tender;
-
the Tender form;
-
the Conditions of Contract; and
-
the Specification.
These parts should be included in all
Government building and construction contract documents.
Agencies must ensure that they use the
up-to-date versions of approved documents, where these exist, when
preparing contract documentation. The agency project manager should
ensure that the project consultants access up-to-date documentation
at the commencement of each project.
The Treasurer's Instructions require
specific documentation to be utilised by agencies as set out
below.
Minor Works
For all minor works construction contracts
valued at $50 000 and over, it is mandatory to use
AS 4905-2002, Minor Works Contract
Conditions.
For minor works contracts valued below
$50 000, it is highly recommended that AS 4905-2002, Minor
Works Contract Conditions is used.AS 4905-2002 is
available to download from the SAI Global website, www.sai-global.com.
For non-construction works, such as
maintenance, agencies should use appropriate Australian Standard
contracts and liaise with the Crown Solicitor to ensure the
contracts are appropriately amended to reflect the
Government's procurement, confidentiality and contractual
policies.
Where an agency is awarding a contract that
may be high risk or require specialised or additional clauses to
those in the standard documentation, it is recommended that the
Crown Solicitor be involved in the drawing up of the contract.
Major Works - Building and
Construction
For all major works construction contracts,
except those where the use of AS 4902-2000 or AS
4300-1995 is appropriate, it is mandatory to use AS
2124-1992, General Conditions of Contract and the Request for
Tender (building and construction version) pro forma documentation
approved by the Crown Solicitor. For procurements that are impacted
by Australian Government funding requirements, agencies must use
the Commonwealth Government Funded Work Version RFT pro forma which
contains all the necessary provisions of the Australian
Government Implementation Guidelines for the National Code of
Practice for the Construction Industry and the Australian
Government Building and Construction OHS Accreditation Scheme.
For non-construction works, such as
maintenance, agencies should use appropriate Australian Standard
contracts and liaise with the Crown Solicitor to ensure the
contracts are appropriately amended to reflect the
Government's procurement, confidentiality and contractual
policies.
Crown Solicitor's pro forma RFT documentation
When undertaking a tender for which the Crown
Solicitor's building construction RFT pro forma is being
used, agencies should firstly check whether their agency has an
appropriate licence to use and amend AS 2124-1992 from SAI
Global. Agencies should then complete and amend Annexures Part A
and Part B to AS 2124-1992 in accordance with the
appropriate Guide to the Completion of Annexures to AS
2124-1992 and attach relevant AS 2124-1992 documentation
to the RFT pro forma. Copies of the Guide for completing the
Commonwealth Government Funded Work Version RFT and the Guide for
completing the standard RFT have been distributed to all agencies
and information on their use can be obtained by contacting the
agency's Procurement Reference Group representative. If
unsure of the name of the Procurement Reference Group
representative for your agency, please contact Treasury at
purchasing@treasury.tas.gov.au.
Standards Australia has produced the
General Conditions of Contract AS 2124-1992 User Guide SAA HB
42-1992. All parties involved in the use of this contract, as
well as agency project managers, should familiarise themselves with
this document.
The User Guide and AS 2124-1992 and
Annexures are available to download from the SAI Global website at
www.sai-global.com.To
obtain a licence for the amendment and use, reproduction and
distribution of SAI Global material, contact SAI Global on (02)
8206 6355 or email copyright@saiglobal.com.
The Crown Solicitor's major works
Request for Tender (building and construction version) document is
made up of four parts -
Conditions of Tender
The Conditions of Tender reflect the
requirements of the Treasurer's Instructions and AS
4120-1994, Code of Tendering. These conditions indicate the
minimum requirements of Government from tenderers. This section
should be included in any Request for Tender unaltered. The
Commonwealth Government Funded Work Version RFT contains additional
tender conditions imposed by Australian Government funding
requirements. If amendments are to be made, the amended document
must be approved by the Crown Solicitor.
Tender Form
The tender form is required to be completed by
all tenderers. It contains the tenderer's declaration of
compliance with the conditions and requirements, a schedule of
specialist contractors (if required), a Government Building and
Construction Training Authority Compliance Declaration and a
Workplace Health and Safety Contractor Management System
Questionnaire. The Commonwealth Government Funded Work Version RFT
contains additional declarations of compliance with Australian
Government funding requirements.
Conditions of Contract including
Annexures
The Conditions of Contract are made up of
-
-
Australian Standard General Conditions of Contract AS
2124-1992;
-
Annexure Part A - the details of the contract;
-
Annexure Part B - details of deletions, amendments or
additions to AS 2124 -1992;
-
Annexure Part C - supplementary conditions of contract;
and
-
Annexure Part D - confidentiality.
This section should be included in any Request
for Tender unaltered. If amendments are to be made, the amended
document must be approved by the Crown Solicitor.
Properly licensed and completed
Annexures Part A and Part B to AS 2124-1992 must be attached
to the Request for Tender prior to distributing to all prospective
tenderers. For instruction on how to obtain licensed Annexures from
SAI Global and how to complete the Annexures, refer to the advice
above.
Specification
The specification contains the technical
requirements for the project.
Major Works - Roads and Bridges
For all major works construction contracts,
except those where the use of AS 4902-2000 or AS
4300-1995 is appropriate, it is mandatory to use AS
2124-1992, General Conditions of Contract and the appropriate
approved Preliminaries/Request for Tender document.
For non-construction works, such as
maintenance, agencies should use appropriate Australian Standard
contracts and liaise with the Crown Solicitor to ensure the
contracts are appropriately amended to reflect the
Government's procurement, confidentiality and contractual
policies.
Further information on the appropriate
documentation is available from DIER.
Consultancies
The contract to be applied to a consultant
commission is AS 4122-2010
General Conditions of Contract
for Consultants, unless a more appropriate contract is deemed
suitable by the Crown Solicitor.
At the planning stage of engaging consultancy
services for relevant projects, agencies must:
-
seek advice from the Office of the Crown Solicitor to:
-
ensure AS 4122-2010 is the appropriate contract to be used for the
circumstances of the particular case; and if so:
-
obtain a copy of the Schedules that have been drafted by the Crown
Solicitor amending the Annexures of AS 4122-2010 for inclusion with
the contract; and
-
advice on how to complete the Annexures to AS 4122-2010; and
-
ensure their agency has an appropriate licence from SAI Global to
use and amend AS 4122-2010 before releasing any quotation or tender
documentation.
The User Guide, AS
4122-2010 and its Annexures are available to download from the
SAI Global website at www.sai-global.com. To
obtain a licence for the amendment and use, reproduction and
distribution of SAI Global material, contact SAI Global on (02)
8206 6355 or email copyright@saiglobal.com.
The design and preparation of works contract
documentation requires the engagement of consultants to perform
this task on behalf of the procuring agency. The consultants
required for the procurement process vary depending on the project
size, nature and complexity. The Best Practice for the Engagement of Consultants,
published by Treasury as part of the Procurement Practices Manual,
provides the best practice process for engaging consultants. Refer
also to the Treasurer's
Instructions 1216.
Contract Administration
The contract is between the Principal and the
contractor. It is the responsibility of the contractor to complete
the works as specified in the contract documents. The
Superintendent ensures that the conditions of contract are adhered
to by the contractor and the Principal.
The Client Agency Project Manager (CAPM) is
not recognised in the contract, but the role is to ensure (on
behalf of the Principal) that both the Principal and the
Superintendent are performing their respective duties under the
contract. These duties include the Superintendent assessing the
contractor's progress payments and the Principal making
progress payments to the contractor based on the
Superintendent's assessments.
To ensure that the conditions of contract are
being followed the client agency is required to setup and manage
internal contract administration systems and procedures (or, if
they already exist, ensure that they function and are
followed).
The Principal in the contract is the Crown in
Right of Tasmania. As any contract will require the Principal
to perform some duties, a specific person must act on behalf of the
Principal. This is usually the person who signs the contract and is
the person who should be kept informed by the Superintendent and
the CAPM of the condition and progress of the contract.
If the agency's Minister signs the
contract, it is usual for the Head of Agency to keep the Minister
informed and the CAPM and Superintendent report to the Head of
Agency. These officers would also report to the Head of Agency when
the Head of Agency acts on behalf of the Principal as the
Principal's Representative.
A contract functions effectively with or
without a Principal's Representative. When the Minister signs
the contract and carries the responsibility for the role of the
Principal, and the Head of Agency needs to keep the Minister
informed of the contract, consideration should be given to
formalising the role of the Head of Agency within the contract as
the Principal's Representative. This enables the Head of
Agency to perform most of the Principal's responsibilities.
When the Head of Agency signs the contract and is responsible for
the role of the Principal, a Principal's Representative may
not be needed.
The duties of the Principal, the
Superintendent and the contractor are generally set out in the
contract. Information on delegation of duties from the Principal to
the Principal's Representative and/or the Superintendent is
set out in Section 3 of the PPM - Contract Documentation, Delegation and Risk.
Managing Contractual
Risk
Risk management is an essential part of the
corporate planning process. The Australian and New Zealand Risk
Management Standard AS/NZS 4360-1995
sets out a
structured approach to risk identification, classification,
analysis and treatment and it is recommended that all asset
managers become familiar with the code.
The PPM - Contract Documentation, Delegation and Risk is
intended as a guide in identifying the commonly encountered major
risks and their consequences. It also sets out to define the
normally accepted responsibilities and delegations for managing
these risks and gives guidance to agency managers in ensuring that
these responsibilities are being met and the risks are being
properly managed.
Delegations
The parties to the contract are the Principal
and the contractor. The roles of the parties are set out in the
PPM - Contract Documentation, Delegation and Risk.
Although a Principal may delegate his powers
and functions under the contract, this does not prevent him from
exercising these powers and functions in his own right. The
Principal remains responsible for the actions, within the contract,
of those to whom he/she has delegated functions. The contractor can
bring charges of breach of contract to the Principal only.
The Principal in a building and construction
contract is normally a Minister or a Head of Agency. Neither would
exercise all the powers allocated to the Principal and would
normally delegate some of these powers to the Principal's
Representative and the Superintendent in the contract.
The agency is responsible for determining and
implementing which contractual duties should be delegated, and to
whom. What is delegated will depend on the person named as the
Principal and his/her availability for involvement in the contract,
as well as depending on agency policy, such as monetary
delegations.
In delegating functions, the Principal must
ensure that the persons undertaking the functions have the
capability to fulfil the requirements of the functions and protect
the Principal against a "breach of contract". In
delegating functions, the Principal must ensure that both an audit
trail and the integrity of the contractor payment process are
maintained.
Generally, under the contract, the contractor
must be notified, in writing, of the functions and powers delegated
and to whom. This notification usually forms part of the tender
documents.
It is expected that in Government contracts
the Principal will delegate most functions.
Resolution of
Contractual Disputes
When two parties enter into a contract,
differences can occur that require dispute resolution
procedures. It is preferable that a dispute is resolved by
the contracting parties. However, when this fails, the dispute must
be resolved with the assistance of third parties. There are various
methods of dispute resolution set out in the PPM - Contract Documentation, Delegation and
Risk.
Some of the methods referred to in that
document are:
-
expert appraisal;
-
mediation;
-
mini-trials; and
-
arbitration and litigation.
Security of Payment Act
The Building and Construction Industry Security of Payment Act
2009 creates a right of payment for people carrying out
building and construction work or supplying related goods or
services under a building and construction contract. Once a payment
claim has been made in the manner required by the Act, unpaid
parties can take advantage of a payment dispute resolution process
called 'adjudication'.
For more information on the Security of
Payment Act go to www.wst.tas.gov.au/industries/building/securityofpayment/resources.
This website provides information on the Act, step-by-step guides
for claimants and respondents, sample forms and lists the
Nominating Authorities.
Crown Contracts
Confidentiality Policy
All contracts arising from a procurement must
comply with the requirements of the Crown Contracts Confidentiality Policy.